Runway 1-19 Rehabilitation Project – Summer/Fall 2026
The anticipated project phasing is shown below. Check NOTAMS for updated closure times and dates.
October 19, 2026 Update: Click on above image to enlarge
- October 5, 2026 – Pavement Grooving began in Phase I (orange area) and will continue from south to north. Phase 4, 5, 6, 2, and 3 will follow in order each was paved. The estimated time is 5 weeks.
- Airport Closure Dates:
- Oct 20,2026 – 12:00 am to 4:00am for runway lighting repairs.
- Nov 1-8, 2026 – 10:00 pm to 7:00am for pavement grooving in Phases 2 and 3
Please note dates and times subject to change due to weather.
5 Parcel Development at Republic Airport
2017 SEQRA Environmental Determination for Parcel Development at Republic Airport
Republic Airport Request For Proposals (RFP) Public Meeting
Response To Public Comments
MARCH 2, 2017 Airport Meeting Slide Show Presentation
Responses to Questions From March 2, 2017 Airport Meeting
Runway 1/19 Runway Safety Area Project
|
November 7, 2018 Runway 1-19 Safety Area Improvements at Republic Airport |