Runway 1-19 Rehabilitation Project – Summer/Fall 2026
The anticipated project phasing is shown below. Check NOTAMS for updated closure times and dates.
August 25, 2026 Update: Click on above image to enlarge
- Phase 1 (orange section) is closed and remains under construction.
- Phase 4 (green section) to start this week. This area, including Taxiways B4, G5, and G6 will be closed for about two weeks. Please Check NOTAMS for exact dates.