Runway 1-19 Rehabilitation Project – Summer/Fall 2026
The anticipated project phasing is shown below. Check NOTAMS for updated closure times and dates.
September 10, 2026 Update: Click on above image to enlarge
- Phases 5 and 6 (blue and light purple sections) to start this week. This area, including Taxiways B2, B3, G2, G3 and G4 will be closed for about one week. Please Check NOTAMS for exact dates.
5 Parcel Development at Republic Airport
2017 SEQRA Environmental Determination for Parcel Development at Republic Airport
Republic Airport Request For Proposals (RFP) Public Meeting
Response To Public Comments
MARCH 2, 2017 Airport Meeting Slide Show Presentation
Responses to Questions From March 2, 2017 Airport Meeting
Runway 1/19 Runway Safety Area Project
|
November 7, 2018 Runway 1-19 Safety Area Improvements at Republic Airport |
